Permit before work
Council states crossover work in the road reserve requires a Road Reserve Works Permit.
Rockhampton Region
Separate private hardstand work from council-controlled road-reserve work.
The section between a property boundary and road is a public-asset interface. Its levels, drainage and construction can be controlled separately from the private driveway.
A driveway crossover (Council also calls it a vehicle crossing or property access) is the part of the driveway between the road and your property boundary: across the kerb and channel or table drain, the verge and any footpath. It sits in Council-controlled road reserve, so it needs Council approval before work starts, even though the property owner pays for it and maintains it. Rockhampton Regional Council applies the Capricorn Municipal Development Guidelines (CMDG) rather than a single Australian Standard, so crossover specifications published for Brisbane or other councils do not carry over.
This guide pulls together Council's forms, fees, drawings and conditions as published when we checked them on 12 October 2026. It is general information. Rockhampton Concreting Co is a referral service: it does not lodge permits, build crossovers or arrange traffic control, and Council or a responding provider confirms what applies to your address.
The right application depends on who controls the road and what kind of driveway you are building.
| Your situation | What applies |
|---|---|
| A standard residential driveway (new, moved or secondary) on a Council-controlled road | One step: Construct a Standard Residential Driveway and/or Residential Stormwater Connection Application Form (RRC407). Council issues a permit if it accepts the works and the traffic and pedestrian arrangements. |
| A commercial, rural (table drain) or non-standard driveway on a Council-controlled road | Two steps: an Install/Alter Private Infrastructure in a Road Reserve Application Form (RRC405) for “in principle” approval, then a Temporary Road/Footpath Closure Application Form (RRC406) before any work starts. Council’s fact sheet also refers industrial, commercial and multi-unit residential driveways to Council’s Duty Planner. |
| The property fronts a State-controlled road | Transport and Main Roads (TMR) approves the access, not Council. TMR requires both a permitted road access location approval and a road access works approval: Form 5083 where there is no development application referred to SARA, or Form 5082 after a SARA development approval. TMR explains the process, including how to check the road on its DAMS map. |
| A private road or community title development | Council’s fact sheet says its approval is only required within Council-controlled road reserves, not on private roads or in community title developments. |
| A second driveway | Needs Council approval. RRC407 says the property frontage must be at least 30 m for a secondary driveway. |
| A property outside Rockhampton Regional Council’s area | Check with the council for that area. Its forms and standards may differ. |
Council’s Property access page explains the owner’s responsibilities. The current application forms are listed on Council’s Customer Forms page under Roads and Infrastructure, so check there for the latest version before you fill one in. RRC407 lists payment in person at Council’s customer service centres in Rockhampton, Mount Morgan and Gracemere, by phone once Council receives the form, or by post.
A printable sequence for a standard residential crossover on a Council road, drawn from RRC407, Council’s driveway fact sheet and CMDG-R-041.
Council charges a fee to assess each application. These are Council’s application fees only, not the cost of building the crossover. For construction pricing, compare written quotes using the Rockhampton concrete cost guide.
| Item (Council fee code) | 2026/27 fee | Notes |
|---|---|---|
| Residential driveway/vehicle access application (CIV010) | $247 | Vehicle access to a single lot with approved estimated works of $30,000 or less. Non-refundable. |
| Commercial driveway/vehicle access application (CIV011) | $247 | Same conditions as CIV010. Non-refundable. |
| Temporary road and/or footpath closure application (CIV016) | $247 | Relevant to the two-step process (RRC406). Non-refundable. |
| Works in road reserve over $30,000 (CIV018) | As assessed | Calculated from the approved estimated cost of works in the road reserve. |
| Permit amendment, minor (CIV019) | 25% of the original fee | Date changes, extensions and very minor adjustments to plans or conditions. |
| Permit amendment, major (CIV020) | 50% of the original fee | Changes that need reassessment. |
| Council supply and installation of concrete crossovers (CIV022) | Private works quote | Quoted by Council case by case; no set fee. |
Rockhampton Regional Council uses the CMDG, a set of standards shared by several Central Queensland councils. The residential drawing is CMDG-R-041 Residential Driveway (Revision F, July 2026, which lists Rockhampton as an applicable council). Rural access over a table drain uses CMDG-R-040, and the design rules sit in CMDG D15 Driveways. Both are free on the CMDG Standard Drawings and Design and Construction Specifications pages. When Council approves an application it issues standard conditions and drawings for an urban or rural crossover, and those govern your job.
| Item | Requirement |
|---|---|
| Width | 2.7 m minimum (3 m preferred), 6 m maximum |
| Kerb tapers | 1,000 mm each side |
| Slab thickness | 125 mm |
| Reinforcement | SL82 mesh, 50 mm top and edge cover |
| Concrete | N32 (to AS 1379 and AS 3600) |
| Dowels to existing concrete | R16 galvanised, 400 mm long at 400 mm centres |
| Expansion joints | 10 mm full-depth closed-cell foam |
| Grade across footpath and verge | Typically 2.5% maximum |
| Ramp at the kerb | 1 in 8 nominal |
| Grade inside the property | 16% desirable maximum, 20% maximum |
| Kerb | Diamond-saw cut, cut down 50 to 100 mm |
| Existing path under 125 mm thick | Remove and replace as part of the crossover |
| Finish | Non-slip (broom finish accepted); no asphalt, loose, stamped or slick finishes in urban areas |
| Intersections (Rockhampton residential) | 10 m unsignalised, 25 m signalised, 20 m roundabout |
| Clearances | 0.6 m stormwater pit, 0.5 m street signs, 1 m trees, poles and guardrail, 2.5 m public transport infrastructure |
The CMDG drawing notes that these crossings are not designed for commercial vehicles. If your site cannot meet the standard drawing, for example because of a steep verge, the applicant must submit an alternative design certified by a Registered Professional Engineer of Queensland (RPEQ) for Council approval before a permit is issued, and D15 puts the associated costs on the applicant.
Council reviews crossovers wider than 6 m individually. CMDG D15 limits driveways by frontage: one driveway up to 3 m wide where the frontage is 10 m or less; one up to 6 m where it is over 10 m but under 30 m; and one extra driveway up to 3 m where an urban frontage exceeds 30 m. Multiple driveways need at least 6 m clear between them at the kerb face.
RRC407 measures intersection distances from the tangent point of the kerb invert on the adjacent street to the nearest edge of the driveway, or for a roundabout from the kerb invert where the nearest leg meets the circulating lane. Hydrants cannot sit within a driveway, the crossover must not cover utility pits or valves, and the CMDG drawing makes relocating conflicting services the property owner’s expense.
The crossover follows the existing footpath profile so pedestrians and overland stormwater are not obstructed, because the footpath and road reserve often carry water in a major flood. Council asks owners of sites with steep footpath crossfalls to liaise with it before building. Where the crossover meets adjoining ground, D15 limits the step to 10 mm against hard surfaces and 25 mm against grass or soil.
The kerb is saw cut along the invert and broken out, including mountable kerb. Council will reject kerb broken out with a sledgehammer and may replace it at the owner’s expense, and the original top-of-kerb level has to be regained within 1.2 m of the driveway so stormwater keeps flowing. A full slab runs across a constructed footpath: wheel strips across the path are not allowed.
Never bridge the gutter with checker plates, timber sleepers or concrete. A bridge from the road edge needs approval as a Bridge Grated Crossover, and grates can be ordered through Council’s Road Infrastructure Private Works Application Form (RRC317) only with a current Road Reserve Works Permit.
A standard residential crossover is concrete only; gravel or a seal is only an option where you access the property from a gravelled or sealed rural road. CMDG D15 says stamped concrete and slick finishes should be avoided, including rounded-pebble exposed aggregate, silicone sealant paint and glossy or ceramic tiles. If you want a decorative finish, plan it for the private driveway inside the boundary; the exposed aggregate guide covers that side of the job.
Where there is no kerb and channel, CMDG-R-040 and D15.12 apply. Rural residential lots generally get one access, at least 20 m from the centre of an intersection or roundabout unless Council approves otherwise. Crossing a table drain usually needs a precast reinforced concrete pipe with sloping headwalls, at least 375 mm diameter Class 3 with 300 mm of cover (or Class 2 with 450 mm of cover), built by a civil contractor with relevant experience and equipment. Multiple pipes or box culverts need an RPEQ-approved design, guideposts mark each end, and a gravel driveway is not permitted where the road is bitumen or asphalt.
Council asks every applicant to explain it. RRC407 requires the details and duration of any road or footpath closure and how traffic and pedestrians will be kept safe. Whether you need a full traffic plan depends on who does the work and how the road and footpath are affected.
A permit is not Council’s endorsement of the traffic plan: the forms state that Council takes no responsibility for the safety or effectiveness of the traffic and pedestrian management you submit.
These are Council’s stated timeframes, not a promise about how long a particular application will take.
The property owner is responsible for building and maintaining the crossover from the road to the boundary, at their own cost. Council’s Property access page says the owner may build the access or engage a private contractor, built to Council’s standards.
After the work, the owner keeps the crossover safe for all road users and keeps drainage paths and any grate clear. Council’s fact sheet says it can issue a compliance notice, or remove or modify features at the owner’s expense, if a driveway is not built or maintained to its standards. If Council later alters a legally constructed crossover for its own roadworks or services, it reinstates the access to an equal or higher standard.
The private driveway inside your boundary is a separate scope with its own design choices; the concrete driveways guide covers that part.
Council’s forms and standards point to these problems. They are what the documents say, not a ranking of how often each happens.
Council states crossover work in the road reserve requires a Road Reserve Works Permit.
The crossing must work with kerb, table drains, footpaths and stormwater paths.
Property conditions and council drawings can change.
The quote should identify who handles applications, inspections or restoration.
Local planning point
Rockhampton Regional Council publishes current property-access and stormwater guidance. Confirm the exact address and proposal before starting.
Useful official sources: Council’s Property access page, its driveway crossover fact sheet (PDF), the Customer Forms page for RRC407, RRC405 and RRC406, the Fees and Charges page, and the CMDG Standard Drawings.
Ask each responding provider to put the proposed scope, assumptions, exclusions and responsibilities in writing. A lower figure is not a saving if it omits preparation, access, disposal, approvals or completion work that another quote includes.
Yes, if the work is in a Council-controlled road reserve. Rockhampton Regional Council says no crossover should be built in the road reserve without applying for a Road Reserve Works Permit. Driveways on State-controlled roads are approved by Transport and Main Roads instead, and Council's approval is not needed on private roads or in community title developments.
For 2026/27 the residential driveway/vehicle access application fee is $247 (non-refundable) for a single lot where the works are estimated at $30,000 or less. Minor permit amendments cost 25% of the original fee and major amendments 50%. This is Council's application fee only, not the cost of building the crossover. Fees are reviewed each July, so confirm the current schedule with Council.
Council's form says to allow up to 10 business days, and the clock only starts once the application is complete. Lodge at least 10 working days before you plan to start; Council recommends 20 working days.
Council's application asks how traffic and pedestrians will be managed during any road or footpath closure. Where a contractor does the work, it asks for temporary traffic management documentation prepared by a competent person. Where the owner does the work personally, simpler plans showing how traffic and pedestrians will be managed may be accepted.
Under the CMDG residential driveway standard the crossover is at least 2.7 m wide (3 m preferred) and no more than 6 m. On frontages of 10 m or less, one driveway up to 3 m is allowed. A second driveway needs Council approval and a frontage of at least 30 m.
Council says the owner may build the access or engage a private contractor, provided it is built to Council's standards after approval. The applicant must be the person doing the work and must provide a certificate of currency for at least $20 million public liability insurance.
One clear enquiry
Describe the property and scope once. Your details can then be referred to a relevant provider servicing Rockhampton Region.